Green hydrogen plant in Woensdrecht: ready to tackle grid congestion
The project investigated the feasibility of a hydrogen production plant at De Leidingstraat in the municipality of Woensdrecht, as part of the Rilland/Woensdrecht Energy Landscape. The plant is designed to utilise renewable electricity from nearby solar parks when the electricity grid is congested. By converting surplus electricity into green hydrogen, grid congestion can be reduced, energy losses due to curtailment can be prevented, and capacity can be freed up for new renewable energy projects.
From exploration to a viable project
Throughout the project, the technical, spatial planning, organisational and financial feasibility was thoroughly assessed. Following a site assessment, one preferred location was selected: Leidingstraat in Woensdrecht.
For this location, a technical design, process design, grid connections, a comprehensive permitting process and various environmental studies were developed. Key agreements were also prepared with the landowner, electricity suppliers and water supplier, among others. The financial model demonstrates the project’s economic viability and formed the basis for an OWE subsidy application.
Permits granted, construction preparations completed
A major outcome of the project is that all required permits have now been granted and are legally final. The project has therefore reached an advanced stage of development in terms of technical, organisational and financial readiness.
The planned electrolyser will have a capacity of 70 MW and is expected to produce approximately 7,900 tonnes of green hydrogen annually. This represents a potential CO₂ reduction of approximately 188,500 tonnes per year. At the same time, the plant will contribute to more efficient use of the electricity grid by absorbing peaks in renewable electricity generation.
Hydrogen offtake
On 26 October 2026, the municipalities of Bergen op Zoom and Woensdrecht, regional industrial partners and H2XP signed an agreement for a joint connection to the hydrogen network in the south-west of the Netherlands. An agreement was concluded with Hynetwork Services B.V. (Gasunie) for this purpose.
Moving towards implementation
Based on the results of the feasibility study, a comprehensive OWE subsidy application has been submitted. Once the subsidy is granted, the final investment decision can be made and construction of the hydrogen production plant can begin.
In parallel, H2XP and its partners are continuing to develop a second location in Rilland, where a smaller hydrogen production plant is being explored that could supply waste heat to the greenhouse horticulture sector.
Want to know more?
The publicly available final report provides a detailed overview of all research findings, technical designs and conclusions of the feasibility study. Read the full final report here.